Friday, October 2, 2015

Drywall, Taped and Primed

The drywall hangers worked very quickly and applied three coats of mud over the course of five days. We used a heater, a dehumidifier, and two oscillating fans to dry out the mud over night between coats. The primed walls look fantastic, and once the siding is up, Joe will move inside and start on the interior trim.